UAB STEAM PROJECT CALENDAR
|
DESCRIPTION Entries in Red are Projected Dates |
PUBLIC ADV DATE |
PREQUAL OF GENERAL CONTR'S |
PRE-BID CONF |
BID DATE |
LETTER OF INTENT |
PRE-CONST CONF |
NOTICE TO PROCEED |
AWARD GENERAL CONTRACT |
COMMENCE CONST |
PROJ. COMP DATE |
060008-GP South Loop Steam Dist (A-1) |
12/22/10 |
1/11/11 |
3/1/11 |
3/17/11 |
3/30/11 |
4/28/11 |
5/23/11 |
Russo Const |
5/24/11 |
10/09/12 |
060008-HP North Loop Steam Dist (A-2) |
12/22/10 |
1/11/11 |
4/26/11 |
5/10/11 |
5/27/11 |
7/21/11 |
8/03/11 |
Brice Building |
8/04/11 |
10/22/2012 |
060008-DP Boilers Purchase (B-1) |
3/4/11 |
RFP BY PURCHSG |
N/A |
3/16/11 |
N/A |
N/A |
Issue P.O. on 6/01/11 |
Babcock & Wilcox Manufact. |
Begin fabrication 6/1/11
|
Complete
|
060008-BP New Steam Plant (B-2) |
1/25/11 |
2/17/11 |
4/7/11 |
5/12/11 |
6/30/11 |
8/16/11 |
8/25/11 |
Stone Building Co., Inc. |
8/26/11 |
05/31/12 |
060008-CP Plant Mech Process (B-3) |
1/25/11 |
2/17/11 |
10/18/11 |
10/27/11 |
11/4/11 |
11/29/11 |
12/14/11 |
Hardy Corporation
|
12/13/11 |
12/05/2012 |
060008-PP Consolidated Condensate Collection (A-8) |
3/2/12 |
4/19/12 |
5/8/12 |
5/24/12 |
|
|
|
|
07/02/12
|
11/30/2012 |
|