From groundbreaking to grand opening, here’s the preliminary timeline for construction of the first phase of the UAB Science and Engineering Complex. The new home for the Departments of Biology and Physics—along with lab and support space for the Department of Chemistry—the building will include 145,784 square feet of instructional, research- and support-laboratory space; classroom space; and faculty and staff office space.

Location

Final budget approvals

February 2020
Location

Bid out for construction

July 2020
Location

Bid approved and final approvals

August 2020
Location

Groundbreaking

Fall 2020
Location

Construction

October 2020 - October 2022
Location

Departments move in

October/November 2022
Location

Classes begin

Fall 2022/Spring 2023